13. Eel pass at Lemsford Mill

Theme: Ecology and management

Objective:

  • Ensure connectivity for fish passage

Project description

This project will design and install an eel pass at Lemsford Mill, to facilitate the movement of this endangered and iconic species.

Eels have declined dramatically over the last few decades and are now listed as Critically Endangered.  Their life cycle requires them to move up and down catchments and out to the open sea.  These movements can be blocked by weirs, locks and other barriers.  This project will design and fit an eel pass to Lemsford Mill, which will allow elvers to bypass this structure and move upstream.

Grid reference: TL21961240
Project lead: Peter Oakenfull
Project partners: Environment Agency
Funding source: TBC
Project start: March 2015
Contact for more information: This email address is being protected from spambots. You need JavaScript enabled to view it.
Graph showing eel declines

Design by LTD Design Consultants and build by Garganey Consulting. Hosting by Stablepoint